The two statements that should be recorded under the Expected dis-benefits heading are:
B. Staff morale will be negatively affected.
E. MFH will lose direct control over the outsourced business functions.
if we opt for "The 2 year delivery time" why not for"An investment of £2.5m is required" one is project duration and the other is project budget not a dis-benefit
The answer C is not correct! The 2 year delivery time, is not a dis-benefit but a timescale. B (and E) must be the answer.
upvoted 4 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ravi_aws
1 year, 5 months agoSolarPRINCE2
3 years, 4 months agoAssima
3 years, 8 months agoAlex_28
3 years, 11 months agohohako
4 years, 2 months agoCiluba
4 years, 3 months agoPrincessPenguin
4 years, 3 months agoTM_
4 years, 5 months agodanyo
4 years, 7 months agodanyo
4 years, 7 months agoPeterE
4 years, 10 months ago