exam questions

Exam PRINCE2-Practitioner All Questions

View all questions & answers for the PRINCE2-Practitioner exam

Exam PRINCE2-Practitioner topic 5 question 107 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner
Question #: 107
Topic #: 5
[All PRINCE2-Practitioner Questions]

The demobilization of staff and equipment is now complete and the project manager has reviewed the time, cost and scope of the project and notified the project board that the project was completed successfully. The project manager has recommended to the project board that the project board should host an informal event to recognize the hard work and determination of the project team in delivering the project. The project board has agreed with this recommendation and has asked the project manager to organize the event.
Which role should be informed that the project board has approved this event?

  • A. Business
  • B. Project executive
  • C. Senior supplier
  • D. Project assurance
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
a4d74be
2 weeks, 3 days ago
Selected Answer: A
Celebrating is part of "Request project closure". Informed for this step should be the Business, team manager and Project supprort. It is A.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago