The demobilization of staff and equipment is now complete and the project manager has reviewed the time, cost and scope of the project and notified the project board that the project was completed successfully. The project manager has recommended to the project board that the project board should host an informal event to recognize the hard work and determination of the project team in delivering the project. The project board has agreed with this recommendation and has asked the project manager to organize the event.
Which role should be informed that the project board has approved this event?