Question #: 46
Topic #: 5
[All PRINCE2-Practitioner Questions]

During the 'starting up a project process', the project manager discusses the standard model for course development with the executive. The project manager then assesses how the Health and Safety Training Project will be delivered, including what products should be delivered in each stage.
Is this an appropriate way to carry out the 'plan the initiation stage' activity, and why?

  • A. Yes, because the work of the initiation stage needs to be planned and approved, in the same way as other project work.
  • B. Yes, because the management controls for the initiation stage need to be defined and approved by the project board.
  • C. No, because subsequent stages are planned in the initiation stage as part of creating the project plan.
  • D. No, because the senior supplier is responsible for assessing the viability of the project approach.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Heidi20
1 week, 2 days ago
Selected Answer: C
C is the answer
upvoted 1 times
...
a4d74be
2 weeks, 2 days ago
Selected Answer: C
The project manager has to do the below when planning initiation stage during starting up a project. Identifying stages is not included. It will be done during initiation stage when creating the project plan. My opinion :) --> decide suitable management controls for the initiation stage activities, based on the project approach. ●  identify any constraints on time and costs for the initiation stage and produce the stage plan for this stage according to the principles and techniques in Chapter 7. ●  review any risks in the project log and assess their impact on the stage plan for the initiation stage. If any new risks are identified (or existing ones have changed), update the project log.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago