exam questions

Exam PRINCE2-Practitioner All Questions

View all questions & answers for the PRINCE2-Practitioner exam

Exam PRINCE2-Practitioner topic 5 question 23 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner
Question #: 23
Topic #: 5
[All PRINCE2-Practitioner Questions]

PROGRESS -
The project board has asked the project manager to produce highlight reports every two weeks during stage 4, as the project is near completion. The standard for the rest of the project was every four weeks.
Which statement explains why this is appropriate?

  • A. The format and content of highlight reports should meet the information needs of the project board.
  • B. Progress reports should be produced at the ad hoc request of the project board during a stage.
  • C. The frequency of reporting should suit the level of risk and the products being created during the stage.
  • D. The frequency of reporting should suit the level of risk and products being created within the work package.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
a4d74be
2 weeks, 4 days ago
Selected Answer: C
What was changed here is the frequency not the content and format. Since the question if refering to a stage it has to be C.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago