exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 262 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 262
Topic #: 1
[All PRINCE2-Foundation Questions]

Identify the missing words in the following sentence.
Project assurance personnel [ ? ] the project manager.

  • A. are able to overturn the decisions of
  • B. must be accountable to
  • C. should support
  • D. report to the project board and
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
a2476d0
1 month, 1 week ago
Selected Answer: D
i think it would be D. Project assurance is independent of the project management team and should report directly to the project board. BUT whatever findings results is also comuunicated to the project manager. Project assurance does not support the project manager as it is a role or the Project support which is part of the project team.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago