Exam PRINCE2 Agile Practitioner topic 1 question 31 discussion

Actual exam question from PRINCE2's PRINCE2 Agile Practitioner
Question #: 31
Topic #: 1
[All PRINCE2 Agile Practitioner Questions]

Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)

Introduction -
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope -
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training

Project Background -
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline -
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.
There are 30 vendor stalls selling products related to the event.
The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
The project manager used the Agilometer to assess the prevailing agile environment and, consequently, took action to improve the low score achieved on the 'flexibility on what is delivered' slider.
When should the project manager undertake a further assessment in order to determine if further action is required to increase the slider score?

  • A. Sprint review.
  • B. Sprint retrospective.
  • C. Release retrospective.
  • D. Project retrospective.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ANNA16
1 month, 1 week ago
Selected Answer: C
The assessment can be reviewed at various times throughout the project – for example, at stage end or after a release – to see if the settings on the Agilometer are happening as predicted.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.