exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 497 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 497
Topic #: 1
[All PRINCE2-Foundation Questions]

The project manager needs to report to the project board on the status of the project’s issues.

Which management product should the project manager review?

  • A. Project log
  • B. Project brief
  • C. Checkpoint report
  • D. Highlight report
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
replyonline
5 days, 6 hours ago
Selected Answer: D
Highlight Report: This is the primary management product used to report on the project's progress and status to the Project Board.
upvoted 1 times
...
Kjennset
1 month ago
Selected Answer: A
A. Project log Explanation: The Project log is the management product that records all the issues, risks, and actions that are raised during the project. It provides a comprehensive overview of ongoing issues and their status, making it the primary document for the project manager to review when reporting to the project board on the status of project issues.
upvoted 1 times
...
skillfulsatellite
1 month, 1 week ago
Selected Answer: A
The Project log is where ongoing issues, risks, actions, and decisions are recorded throughout the project. It provides a comprehensive record of the project's progress, including any issues that need to be tracked and reported. Reviewing the project log allows the project manager to summarize the status of issues, actions taken, and any decisions made, which can then be reported to the project board.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago