Question #: 514
Topic #: 1
[All PRINCE2-Foundation Questions]

How should the ‘progress’ practice be used?

  • A. To define how the products will be delivered to enable control
  • B. To predict whether the benefits will exceed the costs
  • C. To identify opportunities that may make the project more successful
  • D. To deliver change which will benefit people in their day-to-day work
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
A is correct; Here’s why the other options are incorrect: B. To predict whether the benefits will exceed the costs: Incorrect. This relates to the Business Case practice, which focuses on ensuring that the project remains viable, desirable, and achievable. C. To identify opportunities that may make the project more successful: Incorrect. This is addressed by the Risk practice, which deals with identifying and managing risks, including opportunities. D. To deliver change which will benefit people in their day-to-day work: Incorrect. This is the purpose of the project as a whole, but not the specific focus of the Progress practice.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...