Question #: 524
Topic #: 1
[All PRINCE2-Foundation Questions]

The project manager needs to document how risk management will be undertaken during the project.

In which step of the ‘risk management’ technique should the project manager document this?

  • A. Identify: define context and objectives
  • B. Identify: identify threats and opportunities
  • C. Assess: prioritize risks
  • D. Assess: combine risk profile
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Answer A is correct. Why the other options are not correct: B. Identify: identify threats and opportunities: This step focuses on the actual identification of risks, not on documenting the overall approach. C. Assess: prioritize risks: This step involves assessing the probability and impact of risks. D. Assess: combine risk profile: This step involves creating an overall risk profile for the project. Key takeaway: The "Identify: define context and objectives" step of the PRINCE2 risk management technique is where the project manager documents how risk management will be undertaken during the project. This sets the foundation for effective risk management throughout the project lifecycle.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...