The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual products being worked on.
Which part of effective issue management is the project manager applying?
C; Change Control: Change control in PRINCE2 is about managing and controlling any changes to the project's baseline. The baseline is the agreed-upon plan for the project, including the scope, schedule, cost, and the defined products (outputs).
C is correct; A. Baselines: While baselines are important for change control, they are not the specific action being taken by the project manager in this scenario.
B. Change budget: A change budget is used to manage the costs of approved changes, but it's not the primary focus of the project manager's action here.
D. Issue resolution: Issue resolution is about addressing and resolving issues, but the project manager's action is about proactively monitoring for potential deviations before they become major issues.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week agoExamcollectorthanos
1 week agoExamcollectorthanos
1 week ago