Question #: 521
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is the BEST reason for a PRINCE2 project to have at least two stages?

  • A. It enables the project team to close the project in an orderly fashion
  • B. It enables the project board to decide whether to proceed with the delivery of the project product
  • C. It enables the project team to change the scope of the project by agreeing the impact on the business case
  • D. It enables the project board to approve the appointment of external contractors, when required
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
B is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...