A is correct. Why the other options are less suitable:
B. Starting up a project: This process focuses on the initial setup of the project, before the detailed planning of the work.
C. Controlling a stage: This process is about managing the work within a stage, not the initial definition and planning of the major products.
D. Managing product delivery: This process is about the detailed delivery of specific products within a stage, not the overall planning of the major products.