exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 517 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 517
Topic #: 1
[All PRINCE2-Foundation Questions]

Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

  • A. Initiating a project
  • B. Starting up a project
  • C. Controlling a stage
  • D. Managing product delivery
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Examcollectorthanos
1 month, 4 weeks ago
A is correct. Why the other options are less suitable: B. Starting up a project: This process focuses on the initial setup of the project, before the detailed planning of the work. C. Controlling a stage: This process is about managing the work within a stage, not the initial definition and planning of the major products. D. Managing product delivery: This process is about the detailed delivery of specific products within a stage, not the overall planning of the major products.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago