A is correct; Here’s why the other options are incorrect:
B. In a simple project with one work package for the work of a small team: Incorrect. A WBS is less critical for simple projects, as the scope and responsibilities are straightforward and do not require significant decomposition.
C. When establishing a change authority aligned to project tolerances: Incorrect. While the WBS might indirectly help by clarifying project scope, establishing a change authority is not its primary purpose.
D. When assuring business, user, and supplier aspects of project performance: Incorrect. Assuring performance aligns more with roles like the Project Board and assurance functions, not directly with the WBS.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week ago