exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 509 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 509
Topic #: 1
[All PRINCE2-Foundation Questions]

Which TWO are objectives of the ‘starting up a project’ process?

1. To provide an interface between the corporate layer and the project
2. To provide the required authority to initiate the project
3. To plan the work required for project initiation
4. To provide business justification for initiating the project

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Examcollectorthanos
1 month, 1 week ago
Edit it is B
upvoted 1 times
...
Examcollectorthanos
1 month, 1 week ago
This is Wrong, option 4 is not correct. 4. To provide business justification for initiating the project: Incorrect. The business justification is included in the outline business case, but the detailed business case is developed during the Initiating a Project process. I Choose A, since this is the answer in 6th gen exam. Presume it is in 7th aswell.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago