Correct; Why the other options are not correct:
B. Business case: The business case justifies the project and outlines its objectives and benefits, but it doesn't necessarily include the detailed plan for benefit reviews.
C. Quality management approach: This focuses on how the project will ensure the quality of its products, not specifically on measuring benefits.
D. End project report: This report summarizes the project's performance at the end, but it doesn't contain the plan for ongoing benefit reviews.
upvoted 1 times
...