The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.

Which management product should the project manager produce?

  • A. Benefits management approach
  • B. Business case
  • C. Quality management approach
  • D. End project report
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Examcollectorthanos
1 month, 4 weeks ago
Correct; Why the other options are not correct: B. Business case: The business case justifies the project and outlines its objectives and benefits, but it doesn't necessarily include the detailed plan for benefit reviews. C. Quality management approach: This focuses on how the project will ensure the quality of its products, not specifically on measuring benefits. D. End project report: This report summarizes the project's performance at the end, but it doesn't contain the plan for ongoing benefit reviews.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago