The senior user needs to understand how user assurance will support the senior user on the project.

Which management product should the senior user review?

  • A. Project plan
  • B. Project management team structure
  • C. Role descriptions
  • D. Project log
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 1 day ago
C is correct; Why the other options are less suitable: A. Project plan: The project plan outlines the overall plan for the project, but it doesn't provide detailed information about specific roles and responsibilities. B. Project management team structure: This shows the reporting lines and structure of the project team, but it doesn't provide the detailed responsibilities of each role. D. Project log: The project log is a record of events and decisions, not a description of roles and responsibilities.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.