Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 498 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 498
Topic #: 1
[All PRINCE2-Foundation Questions]

According to the ‘exception management’ technique, which roles are MOST LIKELY to identify issues that exceed stage tolerances?

  • A. Project executive AND senior user
  • B. Senior supplier AND team manager
  • C. Project executive AND project manager
  • D. Project manager AND team manager
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 1 day ago
D is correct; Here's why: Exception Management: PRINCE2's exception management technique is about handling situations where the project or a stage goes out of tolerance. This requires identifying potential deviations and escalating them appropriately.   Project Manager's Role: The project manager is responsible for monitoring the overall progress of the stage and checking if it's staying within the agreed tolerances for time, cost, quality, scope, risk, and benefits. Team Manager's Role: The team manager is responsible for managing a team to deliver a work package within a stage. They also monitor their work package's progress and check if it's staying within tolerance. Identifying Exceptions: Both the project manager and the team manager are in positions to identify potential or actual breaches of tolerances. The team manager might identify an issue within their work package that could lead to a stage-level tolerance breach, and the project manager might identify a broader issue affecting the whole stage.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...