Exam PRINCE2-Foundation topic 1 question 494 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 494
Topic #: 1
[All PRINCE2-Foundation Questions]

The project manager is acting as the team manager and needs to control the work of a team member who reports to them.

Which management product should the project manager use to control this work?

  • A. A work package description
  • B. The project management team structure
  • C. A stage plan
  • D. A work breakdown structure
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 1 day ago
A is correct; Why the other options are less suitable: B. The project management team structure: This defines the roles and responsibilities within the project team, not the specific work to be done. C. A stage plan: This is a higher-level plan for the entire stage, not the detailed work of an individual team member. D. A work breakdown structure: This breaks down the project into smaller components, but it doesn't provide the detailed instructions and criteria found in a work package description.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.