A is correct; Why the other options are less suitable:
B. The project management team structure: This defines the roles and responsibilities within the project team, not the specific work to be done.
C. A stage plan: This is a higher-level plan for the entire stage, not the detailed work of an individual team member.
D. A work breakdown structure: This breaks down the project into smaller components, but it doesn't provide the detailed instructions and criteria found in a work package description.
upvoted 1 times
...