Question #: 486
Topic #: 1
[All PRINCE2-Foundation Questions]

What should set the expected success level for benefits, time, cost, quality, scope, sustainability and risk?

  • A. Performance target
  • B. Project baseline
  • C. Integrated elements
  • D. Project context
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 1 day ago
A is correct; \Why the other options are not correct: B. Project baseline: The project baseline is the agreed-upon plan for the project, including its scope, schedule, and cost. It doesn't necessarily define the desired level of achievement. C. Integrated elements: Integrated elements refer to the various components of PRINCE2 (principles, themes, processes, and tailoring), not the performance targets themselves. D. Project context: The project context describes the environment and circumstances surrounding the project, but it doesn't set the specific performance targets.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...