Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 484 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 484
Topic #: 1
[All PRINCE2-Foundation Questions]

The project manager needs to monitor the progress of the stage.

Which combination of management products should the project manager review?

  • A. Checkpoint reports AND work package descriptions
  • B. Project plan AND project log
  • C. Project plan AND work package descriptions
  • D. Highlight report AND checkpoint report
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 1 day ago
Correct; B. Project plan AND project log: The project plan is too high-level for detailed stage monitoring, and the project log is an informal record of events, not a structured progress report. C. Project plan AND work package descriptions: While the work package descriptions are relevant, the project plan doesn't provide the necessary progress updates. D. Highlight report AND checkpoint report: The highlight report is a summary for the project board, not a detailed tool for the project manager to monitor stage progress.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...