Correct; B. Project plan AND project log: The project plan is too high-level for detailed stage monitoring, and the project log is an informal record of events, not a structured progress report.
C. Project plan AND work package descriptions: While the work package descriptions are relevant, the project plan doesn't provide the necessary progress updates.
D. Highlight report AND checkpoint report: The highlight report is a summary for the project board, not a detailed tool for the project manager to monitor stage progress.
upvoted 1 times
...