A is correct; Why the other options are not correct:
B. Project brief: The project brief is a more detailed document that is created during the 'starting up a project' process. It expands on the information in the project mandate.
C. Work package: A work package is a set of tasks assigned to a team, usually within a specific stage of the project.
D. Project approach: The project approach describes the overall strategy and methods that will be used to manage the project.