Question #: 481
Topic #: 1
[All PRINCE2-Foundation Questions]

In the ‘starting up a project’ process, what is the PRINCE2 name for a ‘request for proposal’ received by an external supplier?

  • A. Project mandate
  • B. Project brief
  • C. Work package
  • D. Project approach
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 1 day ago
A is correct; Why the other options are not correct: B. Project brief: The project brief is a more detailed document that is created during the 'starting up a project' process. It expands on the information in the project mandate. C. Work package: A work package is a set of tasks assigned to a team, usually within a specific stage of the project. D. Project approach: The project approach describes the overall strategy and methods that will be used to manage the project.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...