Which are purposes of the “initiating a project” process?

1 To enable the project board to decide whether it is worthwhile to initiate a project
2. To establish solid foundations for a project
3. To enable a project board decision about the commitment of resources to a project
4. To appoint the project management team

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 1 day ago
Initially A, but B is correct; The incorrect options: 1. To enable the project board to decide whether it is worthwhile to initiate a project: Incorrect. This decision is made during the "Starting Up a Project" process, not during "Initiating a Project." 4. To appoint the project management team: Incorrect. The project management team is appointed during the "Starting Up a Project" process as part of the pre-project activities.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...