The correct answer is B. an outcome.
Here's why:
Outputs vs. Outcomes: It's important to distinguish between these two concepts in PRINCE2:
Output: The tangible or intangible deliverable of a project. It's the thing that the project produces.
Outcome: The result or consequence of using that output. It's the change that happens in the business or environment because of the project.
Specialist Product: In PRINCE2, a specialist product is a deliverable of the project, essentially an output.
Change in the Business: When a specialist product is used, it can lead to changes in the business. These changes are the outcomes.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week, 2 days ago