B is correct;
A. project business case: The business case is developed during the "starting up a project" process, not before it.
C. stage plan: Stage plans are created for each individual management stage, not for starting the project as a whole.
D. work package: Work packages are created within stages to authorize specific work, not to start the project.
Identify the missing words in the following sentence.
The ‘starting up a project’ process is triggered when a [?] is available.
A. project business case
B. project mandate
C. stage plan
D. work package
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week, 2 days agoExamcollectorthanos
1 week, 2 days ago