Question #: 432
Topic #: 1
[All PRINCE2-Foundation Questions]

Which management product is used to record relationships between specialist products?

  • A. Change control approach
  • B. Configuration item record
  • C. Issue register
  • D. Product status account
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 2 days ago
Why the other options are incorrect: A. Change Control Approach This describes how changes to the project’s products will be managed but does not record relationships between products. C. Issue Register The Issue Register logs and tracks issues that arise during the project. It does not capture information about product relationships. D. Product Status Account This is a snapshot of the status of products at a specific point in time but does not focus on recording or managing the relationships between products.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...