Exam PRINCE2-Foundation topic 1 question 411 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 411
Topic #: 1
[All PRINCE2-Foundation Questions]

Which PRINCE2 principle is being applied when effective project controls are established?

  • A. Learn from experience
  • B. Manage by exception
  • C. Focus on products
  • D. Defined roles and responsibilities
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 2 days ago
While other principles are relevant, they are not as directly linked to establishing project controls: A. Learn from experience: This is about using past knowledge to improve the project, but not specifically about setting up controls. C. Focus on products: This emphasizes delivering the right products, but not the control mechanisms themselves. D. Defined roles and responsibilities: This is essential for any project, but not the specific principle behind establishing controls for managing by exception.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...