Suggested Answer:A🗳️
Project quality management is the process through which quality is managed and maintained throughout a project. Reference: https://www.globalknowledge.com/us-en/resources/resource-library/articles/what-is-project-quality-management/#gref
The Quality Management Approach in PRINCE2 defines how quality will be managed throughout the project. To meet the minimum requirements for managing quality, it is essential to record the explicit quality criteria for each of the products to be created by the project. This ensures that each product has clear quality standards, which are used to assess whether the product meets the required specifications and satisfies the project's objectives.
A is correct, Why the other options are incorrect:
B. The explicit quality criteria for each of the products to be created by the project
While quality criteria are critical, these are captured in the Product Descriptions rather than the Quality Management Approach. The Quality Management Approach defines the overarching strategy for managing quality, not the specific criteria for individual products.
C. The way the project will use product-based planning to plan quality activities
Product-based planning focuses on identifying and structuring products but does not detail how quality will be managed. The Quality Management Approach is broader and goes beyond just product-based planning.
D. The way that quality management will be communicated throughout the project's life
Communication related to quality is part of the Communication Management Approach, not the Quality Management Approach. The latter focuses on planning and executing quality-related activities.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
replyonline
5 days, 16 hours agoExamcollectorthanos
1 month, 1 week ago