D is correct; The other options are not time-driven controls:
A. End stage report: This is an event-driven control, produced at the end of a stage.
B. Project brief: This is the initial document that triggers the project, not a control mechanism.
C. Project initiation documentation: This is a collection of documents produced during the "starting up a project" process and is not a time-driven control