D = correct; Here’s why the other options are not correct:
A. Controlling a Stage
While Controlling a Stage involves the project manager overseeing progress and addressing issues within a stage, it does not directly provide the project manager with team-level work details, which is the focus of Managing Product Delivery.
B. Directing a Project
Directing a Project is the responsibility of the Project Board and involves overall decision-making and guidance rather than day-to-day details on team activities.
C. Managing a Stage Boundary
Managing a Stage Boundary is used when approaching the end of a stage to review performance and prepare for the next stage, but it is not the process that provides ongoing team-level information.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week, 5 days ago