Question #: 306
Topic #: 1
[All PRINCE2-Foundation Questions]

What process provides information on a team's work to the project manager?

  • A. Controlling a stage
  • B. Directing a project
  • C. Managing a stage boundary
  • D. Managing product delivery
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 5 days ago
D = correct; Here’s why the other options are not correct: A. Controlling a Stage While Controlling a Stage involves the project manager overseeing progress and addressing issues within a stage, it does not directly provide the project manager with team-level work details, which is the focus of Managing Product Delivery. B. Directing a Project Directing a Project is the responsibility of the Project Board and involves overall decision-making and guidance rather than day-to-day details on team activities. C. Managing a Stage Boundary Managing a Stage Boundary is used when approaching the end of a stage to review performance and prepare for the next stage, but it is not the process that provides ongoing team-level information.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...