B = Correct
Here’s why the other options are not correct:
A. Corporate, programme management or customer
While corporate or program management may set high-level expectations and requirements, the specific level of management control for the project itself is set by the Project Board in alignment with these expectations.
C. Project manager
The Project Manager is responsible for applying the controls specified by the Project Board but does not decide the level of management control.
D. Project assurance
Project Assurance provides independent assurance to the Project Board that controls are being applied correctly but does not set these control levels.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week, 5 days ago