Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 303 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 303
Topic #: 1
[All PRINCE2-Foundation Questions]

During the 'initiating a project' process, who specifies the required level of management control?

  • A. Corporate, programme management or customer
  • B. Project board
  • C. Project manager
  • D. Project assurance
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 5 days ago
B = Correct Here’s why the other options are not correct: A. Corporate, programme management or customer While corporate or program management may set high-level expectations and requirements, the specific level of management control for the project itself is set by the Project Board in alignment with these expectations. C. Project manager The Project Manager is responsible for applying the controls specified by the Project Board but does not decide the level of management control. D. Project assurance Project Assurance provides independent assurance to the Project Board that controls are being applied correctly but does not set these control levels.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...