During the 'initiating a project' process, who specifies the required level of management control?

  • A. Corporate, programme management or customer
  • B. Project board
  • C. Project manager
  • D. Project assurance
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
replyonline
5 days, 16 hours ago
"Project Board Authority: The Project Board is the ultimate decision-making authority for the project. They are responsible for ensuring the project aligns with organizational objectives and delivers the expected benefits. While other stakeholders like corporate management, program management, or the customer may provide input, it is the Project Board that ultimately decides on the specific level of management control for the project."
upvoted 1 times
...
Examcollectorthanos
1 month, 2 weeks ago
B = Correct Here’s why the other options are not correct: A. Corporate, programme management or customer While corporate or program management may set high-level expectations and requirements, the specific level of management control for the project itself is set by the Project Board in alignment with these expectations. C. Project manager The Project Manager is responsible for applying the controls specified by the Project Board but does not decide the level of management control. D. Project assurance Project Assurance provides independent assurance to the Project Board that controls are being applied correctly but does not set these control levels.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago