Question #: 277
Topic #: 1
[All PRINCE2-Foundation Questions]

Identify the missing words in the following sentence.
The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.

  • A. benefits, change, risk,
  • B. benefits, quality, risk,
  • C. change, quality, risk,
  • D. benefits, change, quality,
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
http://prince2.wiki/Introduction:_The_PRINCE2_Foundation_Training_Manual

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
B: But in 7th Edition currently there is one more aspect ' Sustainability' .
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...