Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 249 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 249
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is an objective of the 'directing a project' process?

  • A. To review and approve a project mandate
  • B. To ensure corporate or programme management has an interface to the project
  • C. To define how risks, issues and changes will be managed
  • D. To obtain approval for completed products
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
http://prince2.wiki/Directing_a_Project#Objective

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
B; The 'directing a project' process in PRINCE2 emphasizes the importance of clear communication and alignment between the project and the wider organization or program, with the project board acting as the key interface
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...