What is an advantage of dividing the project into stages?

  • A. Detailed plans can be prepared closer to the time events will take place
  • B. the project board can delegate management of the project to team managers
  • C. The project can be authorized by the project manager on a stage by stage basis
  • D. The project brief can be updated towards the end of each stage
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
A = correct; Planning in stages allows for greater accuracy: As you move through a project, you gain more knowledge and understanding. By planning in stages, you can create more detailed and accurate plans for upcoming work because you're closer to the execution of those tasks. This reduces uncertainty and allows for better use of resources.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...