exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 527 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 527
Topic #: 1
[All PRINCE2-Foundation Questions]

The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.

  • A. Starting up a project
  • B. Initiating a project
  • C. Directing a project
  • D. Managing a stage boundary
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Sam_femi
1 week ago
Selected Answer: B
The correct answer is B. Initiating a project. During the initiating phase, key information is gathered and presented to the project board to help them decide whether to proceed with the detailed planning of the project. This phase includes defining the project's objectives, scope, and key stakeholders, and preparing the business case or project brief for approval.
upvoted 1 times
...
Kjennset
1 month, 2 weeks ago
Selected Answer: A
In PRINCE2, Starting up a project is the process where the project manager defines key information, such as the project's objectives, scope, and potential benefits. This information allows the project board to make an informed decision about whether to proceed with more detailed planning. During this process, the project board assesses the project’s viability and whether it aligns with the organization's strategy and goals.
upvoted 1 times
...
skillfulsatellite
1 month, 3 weeks ago
Selected Answer: A
The activity described relates to the ‘starting up a project’ process, specifically the preparation of the Project Brief, which provides the key information required for the project board to decide whether to proceed to the ‘initiating a project’ process.
upvoted 1 times
...
Examcollectorthanos
1 month, 4 weeks ago
A. B. Initiating a project: This process involves detailed planning, which happens after the project board has given the go-ahead in the 'starting up a project' process. C. Directing a project: This process is about the project board's overall guidance and authorization of the project, not the initial decision to proceed with detailed planning. D. Managing a stage boundary: This process occurs at the end of each stage, not at the very beginning of the project.
upvoted 1 times
...
3578791
2 months, 1 week ago
A. Starting up a Project process involves defining the key information necessary to justify and assess whether the project should proceed to the next stage (i.e., to initiate the project in more detail). This includes compiling the Project Brief, which contains high-level information about the project, including objectives, scope, risks, costs, and potential benefits. The goal is to provide the Project Board with enough information to make a decision on whether to move forward with detailed planning.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago