Which is a minimum requirement when applying the “business case” theme?

  • A. Defining the alternative business options for the project in the benefits management approach
  • B. Using lessons to assist in the development of the project business justification and reassessment
  • C. Defining the role of business assurance to monitor the business case against external events
  • D. Updating the business case as soon as new issues and risks are identified
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Sam_femi
2 months ago
Selected Answer: B
The correct answer is B. Using lessons to assist in the development of the project business justification and reassessment. In PRINCE2, the Business Case theme is crucial for ensuring that the project remains viable and justifiable throughout its lifecycle. One of the minimum requirements of this theme is that lessons learned from previous projects are used to inform and improve the development of the business case, as well as its ongoing reassessment. This helps ensure that the business case remains relevant and aligned with the project's goals and objectives.
upvoted 2 times
...
skillfulsatellite
3 months ago
Selected Answer: B
PRINCE2 emphasizes using lessons learned from previous projects to help in the development and ongoing reassessment of the business case. This ensures that the business justification remains valid throughout the project and that decisions are informed by past experiences.
upvoted 1 times
...
Examcollectorthanos
3 months, 1 week ago
B is correct; In PRINCE2, the Business Case theme ensures that the project is aligned with organizational objectives and provides a viable justification for its initiation and continuation. The minimum requirements for applying the Business Case theme include: Ensuring there is a valid business justification for the project. Using lessons learned to develop and reassess the business justification throughout the project.
upvoted 1 times
...
3578791
3 months, 2 weeks ago
The correct answer is B A minimum requirement in the PRINCE2 Business Case theme is to use lessons learned from previous projects to help develop and continuously reassess the business justification. This ensures that the business case remains relevant and that past experiences inform current decisions, contributing to the project's overall viability and alignment with organizational goals.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago