C - A change budget should fund an agreed change to a project's scope. A change budget is a set amount of money that a customer and supplier agree to use to cover the costs of requests for change
A change budget is typically allocated to fund changes that have been formally agreed upon and approved, including changes to the project scope. These changes go beyond the initial plan and require additional resources, thus needing specific budget allocation
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
3578791
3 weeks, 3 days agochristianwill
3 months agoLaserboy
3 months, 3 weeks ago