Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 438 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 438
Topic #: 1
[All PRINCE2-Foundation Questions]

Which management level should approve a course of action if project-level tolerance is exceeded?

  • A. Corporate, programme management or the customer
  • B. Project board
  • C. Project manager
  • D. Team manager
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
bes_i
2 months, 4 weeks ago
Selected Answer: B
B. Project board In PRINCE2, the Project Board is responsible for approving any course of action when the project exceeds its tolerances. This level of management oversees the project’s overall direction and makes decisions regarding significant deviations from the project plan, ensuring that the project remains aligned with its business case and objectives.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...