In PRINCE2, if project-level tolerance is exceeded, the Project Board is responsible for approving a course of action. The Project Board has the authority to make decisions when tolerances set for time, cost, scope, or risk are breached at the project level. This escalates the issue beyond the Project Manager’s authority and requires the Project Board to assess the situation, decide on corrective actions, or, if necessary, escalate further to corporate or programme management.
B. Project board
In PRINCE2, the Project Board is responsible for approving any course of action when the project exceeds its tolerances. This level of management oversees the project’s overall direction and makes decisions regarding significant deviations from the project plan, ensuring that the project remains aligned with its business case and objectives.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Kjennset
3 weeks, 5 days agobes_i
4 months ago