This plan includes the detailed design of the process model, systems model, operating model and organization model.
A. Plan description
A monthly stage status report will be provided to the Project Board.
F. Monitoring and control
The high-level model, produced in the feasibility study by the management consultant, will be used by the project.
B. Plan prerequisites
The Project Board has approved the recommendation to outsource both the Information Technology Division and the Facilities Division to one service provider and this decision must remain in place.
D. Planning assumptions
Based on advice from the Ministry of Trade and Industry that, in their experience, drafting a service level agreement is a lengthy process, allowances have been made for this in the Stage Plan for stage 2.
E. Lessons incorporated
Time: +2 weeks / -2 weeks.
H. Tolerances
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
mcesarlara
4 months, 1 week ago