Question #: 6
Topic #: 5
[All PRINCE2-Practitioner Edition 6 Questions]

Who is responsible for committing user resources to the project?

  • A. Senior User
  • B. Senior Supplier
  • C. Executive
  • D. Project Board
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
mcesarlara
4 months, 1 week ago
Selected Answer: A
The Senior User is responsible for committing user resources to the project, ensuring that the users' needs are represented and that the necessary resources are available to support the project.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...