Which two statements about tailoring the business case in an agile environment are CORRECT?
1. It should be unnecessary because products of the highest value will be delivered first.
2. It should identify the minimum viable product and when it will be delivered.
3. It should take into account that the scope may be reduced during the course of the project.
4. It should show the features, the order in which they will be delivered and any dependencies.

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
LineLar
3 months ago
B. The business case is mandatory in Prince2. 9.3 The business case should clearly state what the minimum viable product is and may give an indication of when this will be delivered ... 9.5 In Prince2 Agilw the business (case) needs to be flexible and written on the assumption that what is being delivered will change ...
upvoted 1 times
...
mohoceima
8 months ago
Selected Answer: D
rdfgdfgdfgfdgdf
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...