Exam PRINCE2 Agile Foundation topic 1 question 19 discussion

Actual exam question from PRINCE2's PRINCE2 Agile Foundation
Question #: 19
Topic #: 1
[All PRINCE2 Agile Foundation Questions]

Which is a purpose of the 'controlling stage' process?

  • A. To execute and deliver the project product
  • B. To establish whether the project is complete
  • C. To report stage progress to the project board
  • D. To draft the plan for the next stage's work
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_117&showNav=true&expandNav=true#:~:text=The%20purpose%20of%20the%
20Controlling,the%20stage%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Esmee93
8 months, 2 weeks ago
C is Correct. Prince2 Agile Axelos book chapter 19.1: "The purpose of the controlling a stage process is to assign work to be done, monitor such work, deal with issues, report progress to the project board, and take corrective actions to ensure that the management stage remains within tolerance."
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.