A is correct; Why the other options are not the primary purpose:
B. To report progress towards the delivery of a stage's products to the project board: This is typically done through highlight reports and end stage reports.
C. To recognize that the project has no further contribution to make towards achieving project objectives: This is determined during the 'closing a project' process.
D. To plan how the project will approach the work to deliver the project products: This is done during the planning stages of the project, not specifically within the 'managing product delivery' process.
17.1 Purpose:
The purpose of the process of managing product delivery is to control the link between the project manager and the team manager. This is achieved by agreeing the requirements for acceptance, execution, reporting, and delivery of specialist products. The role of the team manager is to coordinate an area of work that will deliver one or more of the specialist products that form the project product. Team managers can be internal or external to the organization running the project.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week ago2c8f34d
9 months ago