Question #: 470
Topic #: 1
[All PRINCE2-Foundation Questions]

Which stakeholder interest does the supplier representative represent?

  • A. Those who will use the project outputs to deliver forecasted benefits
  • B. Those providing administrative services and advice during the project
  • C. Those ensuring the project delivers value for money during the project
  • D. Those providing maintenance and support services after project closure
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Sam_femi
5 days, 3 hours ago
Selected Answer: C
The correct answer is C. Those ensuring the project delivers value for money during the project. In PRINCE2, the supplier representative represents the interests of the suppliers and contractors involved in the project, ensuring that the project delivers value for money. Their focus is typically on ensuring the project's products are delivered efficiently, within budget, and meet the agreed-upon quality and specifications. They are primarily concerned with the delivery aspects, such as cost control, resource management, and supplier performance.
upvoted 1 times
...
Examcollectorthanos
1 month, 1 week ago
Id vode D aswell; C. Those ensuring the project delivers value for money during the project: Incorrect. This describes the business interest, which focuses on ensuring that the project provides value for money and remains aligned with the organization’s objectives. D. Those providing maintenance and support services after project closure: Correct. Supplier representatives are involved in delivering the project’s products and may also represent the interests of those responsible for ongoing maintenance and support post-project.
upvoted 1 times
...
Kjennset
1 month, 4 weeks ago
Selected Answer: C
The supplier representative's primary interest is in ensuring that the project delivers value for money, particularly in terms of the resources and services they provide. They are concerned with the cost-effectiveness and efficiency of the project to ensure that the supplier’s contributions meet the project’s requirements and expectations. This interest aligns with their role in overseeing the delivery of products and services that fulfill the project’s objectives while adhering to budget constraints.
upvoted 1 times
...
tnwaogwugwu
9 months, 4 weeks ago
Selected Answer: D
The answer is D
upvoted 1 times
...
tnwaogwugwu
9 months, 4 weeks ago
The answer is D
upvoted 1 times
...
monkeybrain23
10 months, 1 week ago
I think it is D. 7.2.1.4 Senior supplier The senior supplier represents the interests of those designing, developing, facilitating, procuring and implementing the project product. This role is accountable for the quality of products delivered by the supplier(s) and is responsible for the technical integrity of the project. This role will include providing supplier resources to the project and ensuring that proposals for designing and developing the products are feasible and realistic. In many cases, the senior supplier also represents the interests of those who will provide the maintenance services for the specialist products after closure of the project (e.g. engineering maintenance and support). Exceptions to this do occur, however (e.g. when the maintenance services are provided by the customer organization, such as an internal IT department, or are outsourced to a different supplier).
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago