Exam PRINCE2-Foundation topic 1 question 433 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 433
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a minimum requirement for applying the ‘change’ theme?

  • A. Specify in the change control approach the means by which project products will be protected
  • B. Document the format and contents of the issue register
  • C. Produce issue reports to document the impact assessment for requests for change
  • D. Delegate the change authority to the senior supplier(s) for supplier off-specifications
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 2 days ago
B is correct; Why other options are not minimum requirements: A. Specify in the change control approach the means by which project products will be protected: While important, this is not the most fundamental requirement for the change theme. C. Produce issue reports to document the impact assessment for requests for change: Issue reports can be useful, but they are not the minimum requirement for applying the change theme. D. Delegate the change authority to the senior supplier(s) for supplier off-specifications: While delegation is possible, it's not a minimum requirement.
upvoted 1 times
...
monkeybrain23
9 months ago
I think it is A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...