B is correct; Why other options are not minimum requirements:
A. Specify in the change control approach the means by which project products will be protected: While important, this is not the most fundamental requirement for the change theme.
C. Produce issue reports to document the impact assessment for requests for change: Issue reports can be useful, but they are not the minimum requirement for applying the change theme.
D. Delegate the change authority to the senior supplier(s) for supplier off-specifications: While delegation is possible, it's not a minimum requirement.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.