Exam PRINCE2-Foundation topic 1 question 504 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 504
Topic #: 1
[All PRINCE2-Foundation Questions]

When does the ‘directing a project’ process start?

  • A. When the project manager submits the project brief for approval
  • B. When the request to authorize a project is received
  • C. After the project has been authorized by the business layer
  • D. After the project mandate has been received
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
chucks101
1 week ago
Selected Answer: A
the answer is A. The management product established in the starting up a project triggers the directing a project process. This management product are the project brief, the stage plan and the business case. D= project mandate triggers the starting up a project process B= Authorising a project can only be done if the management product like project brief are being established and it is this management products like project brief, stage plan and business case that will be submitted that triggers the directing a project process.
upvoted 1 times
...
selimbeyhan
2 weeks, 4 days ago
Selected Answer: D
D. After the project mandate has been received Explanation: The ‘directing a project’ process in PRINCE2 is performed by the project board and begins after the project mandate has been received. The project mandate is the initial document that triggers the project and provides the authority to start the pre-project activities.
upvoted 1 times
...
Sam_femi
1 month ago
Selected Answer: B
B is the correct answer The Directing a Project process in PRINCE2 starts when the project board receives a request to authorize the project, which typically happens after the Starting up a Project process has been completed and the project brief is submitted for consideration. The project board then assesses whether to approve the project and proceed to the Initiating a Project process.
upvoted 1 times
...
Examcollectorthanos
3 months ago
B is correct; Why the other options are not correct: A. When the project manager submits the project brief for approval: The project brief is part of the PID, and its submission is part of the 'initiating a project' process, not the trigger for 'directing a project'.   C. After the project has been authorized by the business layer: The 'directing a project' process includes the authorization by the project board (which represents the business layer).   D. After the project mandate has been received: The project mandate triggers the 'starting up a project' process, not 'directing a project'.
upvoted 1 times
...
costin31
1 year ago
Selected Answer: B
"The PRINCE2 Directing a Project process starts when the Starting Up a Project process completes and is triggered by the request from the project manager to initiate a project."
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.