B is correct;
Why the other options are not correct:
A. When the project manager submits the project brief for approval: The project brief is part of the PID, and its submission is part of the 'initiating a project' process, not the trigger for 'directing a project'.
C. After the project has been authorized by the business layer: The 'directing a project' process includes the authorization by the project board (which represents the business layer).
D. After the project mandate has been received: The project mandate triggers the 'starting up a project' process, not 'directing a project'.
"The PRINCE2 Directing a Project process starts when the Starting Up a Project process completes and is triggered by the request from the project manager to initiate a project."
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week agocostin31
9 months, 2 weeks ago