exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 244 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 244
Topic #: 1
[All PRINCE2-Foundation Questions]

Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?

  • A. Defined roles and responsibilities
  • B. Learn from experience
  • C. Manage by exception
  • D. Focus on products
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://www.prince2primer.com/academy/uncategorized/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
selimbeyhan
3 weeks, 3 days ago
Selected Answer: B
The PRINCE2 principle that helps to address the concern that the project team may not have worked on a similar project is: B. Learn from experience. This principle emphasizes the importance of learning from past projects, both successes and failures, to improve current and future project performance. If the team lacks experience with similar projects, they can seek lessons from other projects, industry best practices, or external sources to guide their approach and decision-making. This helps mitigate risks and increases the likelihood of project success.
upvoted 1 times
...
MarkNeedsToGo
1 month, 4 weeks ago
Selected Answer: B
Principle 2: Learn from experience PRINCE2 encourages project managers to continuously learn throughout the project, building upon experiences from each stage and previously delivered projects. The teams need to establish a system that captures these experiences and documents them for future referencing, maximising the benefits of both positive and negative experiences.
upvoted 1 times
...
Examcollectorthanos
3 months, 2 weeks ago
These answers are all wrong, first principle; Ensure continued business justification A PRINCE2 project has business justification sufficient to warrant investment to initiate the project and ongoing investment through to successful completion. If it does not, it should be stopped.
upvoted 1 times
...
DANNYPMP
6 months, 1 week ago
Selected Answer: B
Learn from Experience
upvoted 1 times
...
HelgeFFM
1 year, 1 month ago
Selected Answer: A
I would argue that this is not about lessons learned but about the names and structures. Hence it is A. But I did not check the book yet.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago