Question #: 27
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a purpose of the Controlling a Stage process?

  • A. Assign work to be done and take corrective action to ensure that the stage remains within tolerance
  • B. Provide a fixed reference point at which acceptance for the project product is confirmed
  • C. Enable the Project Board to be provided with sufficient information to authorize the next stage
  • D. Enable the organization to understand the work that needs to be done to deliver the project's products
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
btrcbbb34
1 week, 6 days ago
Selected Answer: A
"The purpose of the Controlling a Stage process is to assign work to be done, monitor such work, handle issues, report progress to the Project Board, and take corrective actions to ensure that the stage remains within the tolerances set by the Project Board"
upvoted 1 times
...
HelgeFFM
7 months, 2 weeks ago
why not D?
upvoted 1 times
...
peppe
2 years, 10 months ago
A is correct
upvoted 1 times
...
ejaymac
4 years, 1 month ago
Yes it is a repeat
upvoted 1 times
...
ismailmian123
4 years, 7 months ago
it is a repeated question
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago