Which statement BEST describes the PRINCE2 Agile guidance for change?

  • A. The delivery team should be authorized to make changes at the detailed level
  • B. The delivery team should quickly approve changes to the project baseline
  • C. The executive should manage changes dynamically at the detailed level
  • D. The executive should approve delivery level changes to harness the benefits of positive change
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Old_Jedi
10 months, 3 weeks ago
The most appropriate answer is "D"
upvoted 1 times
...
Vijay29
1 year ago
D. The executive should approve delivery level changes to harness the benefits of positive change In PRINCE2 Agile, the guidance for change involves the executive (represented by the project board) approving delivery level changes to ensure that positive changes can be harnessed while maintaining control over the project. This aligns with the principle of "focus on products" and the need to adapt dynamically to changing circumstances.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...