What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

  • A. Configuration Item Record
  • B. Quality Register
  • C. Highlight Report
  • D. Checkpoint Report
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Community vote distribution
D (100%)

Comments

Chosen Answer:
This is a voting comment. You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
omande
3 months, 1 week ago
Selected Answer: D
A.4.2: A checkpoint report includes a Work Package Tolerance status, used to assess how the execution of the work package is performing against its tolerances (e.g. cost/time/scope actuals and forecast).
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
CISM
New York, 1 minute ago