Question #: 83
Topic #: 1
[All PRINCE2-Foundation Questions]

Whose approval is needed to replace a Stage Plan with an Exception Plan?

  • A. Corporate or programme management
  • B. Project Board
  • C. Project Manager
  • D. Team Manager
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
omande
2 months, 3 weeks ago
Selected Answer: B
C.1: During the project, the project board should approve exception plans when management-stage-level tolerances are forecast to be exceeded.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.