Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 83 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 83
Topic #: 1
[All PRINCE2-Foundation Questions]

Whose approval is needed to replace a Stage Plan with an Exception Plan?

  • A. Corporate or programme management
  • B. Project Board
  • C. Project Manager
  • D. Team Manager
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
omande
1 year, 1 month ago
Selected Answer: B
C.1: During the project, the project board should approve exception plans when management-stage-level tolerances are forecast to be exceeded.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...